With mixed feelings Jan and I left Conway on September 25 for three weeks in Europe, including two weeks of antiques shopping in England.
_______________________________________________________________________________________________________________________________________
Although Jesse Brown's magnificent frame was completed, the timbers were exposed to the elements, and the antiques and tools that we'd moved to the basement were protected only by an array of tarps.
_______________________________________________________________________________________________________________________________________
Work on the roof began soon after our departure.
_______________________________________________________________________________________________________________________________________
Tyler Stosz and a capable crew began by attaching the skip-boarding . .
_______________________________________________________________________________________________________________________________________
to which these cedar shingles would be nailed.
_______________________________________________________________________________________________________________________________________
Applying shingles to the roof of the lean-to was completed first,
_______________________________________________________________________________________________________________________________________
followed by the remainder of the west-facing roof.
____________________________________________________________________________
While the roofers worked outside, Jim McRae and the elusive Mike Woodbury installed the upper level subfloor,
____________________________________________________________________________
giving the first floor its ceiling and the barn its first signs of enclosure.
____________________________________________________________________________
Jesse Brown, applying a final chemical treatment to the frame
____________________________________________________________________________
Some of the 2" by 6" lumber that would frame the outer walls of the barn.
____________________________________________________________________________
____________________________________________________________________________
The west and north walls on the first floor - framed and ready for sheathing
____________________________________________________________________________
Nick Potter works on the driveway that will provide access to the lean-to,
____________________________________________________________________________
while his son Will provides appropriate supervision from above.
____________________________________________________________________________
Framing nearly complete on the east-facing entry side,
____________________________________________________________________________
and complete on the north,
____________________________________________________________________________
and west sides.
____________________________________________________________________________
Home again.
____________________________________________________________________________
Most of the photographs above were taken during our absence by Maggy Sawma Potter, friend and co-conspirator.
____________________________________________________________________________
Click HERE for the next installment.